nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #11

Who is responsible for ensuring that the value-for-money solution is constantly reassessed?

The correct answer is A. Business Assurance. Explanation/Reference:

Organization

Question

Who is responsible for ensuring that the value-for-money solution is constantly reassessed?

Options

  • ABusiness Assurance
  • BSenior User
  • CCorporate or Programme Management
  • DReject Support

How the community answered

(29 responses)
  • A
    83% (24)
  • B
    3% (1)
  • C
    10% (3)
  • D
    3% (1)

Explanation

Explanation/Reference:

Topics

#Business Assurance#value for money#project assurance roles#Organization

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice