PRINCE2-PRACTITIONER · Question #31
In which Management product would the Project Board specify where the authority for change requests lies?
The correct answer is D. Configuration Management Strategy. Explanation/Reference:
Change
Question
In which Management product would the Project Board specify where the authority for change requests lies?
Options
- ARisk Management Strategy
- BQuality Management Strategy
- CCommunication Strategy
- DConfiguration Management Strategy
How the community answered
(49 responses)- A12% (6)
- B2% (1)
- C6% (3)
- D80% (39)
Explanation
Explanation/Reference:
Topics
#Configuration Management Strategy#change authority#Change theme#change control