In which Management product would the Project Board specify where the authority for change requests lies?

The correct answer is D. Configuration Management Strategy. Explanation/Reference:

Change

Question

In which Management product would the Project Board specify where the authority for change requests lies?

Options

  • ARisk Management Strategy
  • BQuality Management Strategy
  • CCommunication Strategy
  • DConfiguration Management Strategy

How the community answered

(49 responses)
  • A
    12% (6)
  • B
    2% (1)
  • C
    6% (3)
  • D
    80% (39)

Explanation

Explanation/Reference:

Topics

#Configuration Management Strategy#change authority#Change theme#change control