PRINCE2
PRINCE2-PRACTITIONER · Question #104
In which strategy would the change control process be recorded?
The correct answer is A. A Change Authority. If the Project Board are too busy to authorize all change requests themselves they can appoint? Explanation/Reference:
Change
Question
In which strategy would the change control process be recorded?
Options
- AA Change Authority
- BA Change Board
- CA Change Committee
- DA Change Budget
How the community answered
(50 responses)- A70% (35)
- B4% (2)
- C20% (10)
- D6% (3)
Explanation
If the Project Board are too busy to authorize all change requests themselves they can appoint? Explanation/Reference:
Topics
#Configuration Management Strategy#change control procedure#Change Authority
Community Discussion
No community discussion yet for this question.