PRINCE2-PRACTITIONER · Question #104

In which strategy would the change control process be recorded?

The correct answer is A. A Change Authority. If the Project Board are too busy to authorize all change requests themselves they can appoint? Explanation/Reference:

Change

Question

In which strategy would the change control process be recorded?

Options

  • AA Change Authority
  • BA Change Board
  • CA Change Committee
  • DA Change Budget

How the community answered

(50 responses)
  • A
    70% (35)
  • B
    4% (2)
  • C
    20% (10)
  • D
    6% (3)

Explanation

If the Project Board are too busy to authorize all change requests themselves they can appoint? Explanation/Reference:

Topics

#Configuration Management Strategy#change control procedure#Change Authority