PRINCE2-PRACTITIONER · Question #107

When examining a project issue, which three aspects should be considered? 1. Performance targets 2. Business Case 3. Resources 4. Risk

The correct answer is C. 1, 2, 4. Explanation/Reference: Impact analysis of an issue should consider: project performance targets, business case, dependent products produced by project, project risk profile.

Change

Question

When examining a project issue, which three aspects should be considered? 1. Performance targets 2. Business Case 3. Resources 4. Risk

Options

  • A1, 3, 4
  • B2, 3, 4
  • C1, 2, 4
  • D1, 2, 3

How the community answered

(34 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    82% (28)
  • D
    9% (3)

Explanation

Explanation/Reference: Impact analysis of an issue should consider: project performance targets, business case, dependent products produced by project, project risk profile.

Topics

#issue examination#Business Case#performance targets#risk