nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #204

The configuration of the final deliverable of the project is -

The correct answer is D. The sum total of its products. Explanation/Reference:

Change

Question

The configuration of the final deliverable of the project is -

Options

  • AThe single end product
  • BThe interim products
  • CIts product description
  • DThe sum total of its products

How the community answered

(36 responses)
  • A
    6% (2)
  • B
    14% (5)
  • C
    3% (1)
  • D
    78% (28)

Explanation

Explanation/Reference:

Topics

#configuration management#product configuration#final deliverable#project products

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice