PRINCE2-PRACTITIONER · Question #203
which step is NOT part of "Accepting a Work Package"?
The correct answer is C. Monitor and control the risks associated with the Work Package. Explanation/Reference:
Managing Product Delivery
Question
which step is NOT part of "Accepting a Work Package"?
Options
- AUnderstand the reporting requirements
- BAgree tolerance margins for the Work Package
- CMonitor and control the risks associated with the Work Package
- DProduce a Team Plan which shows that the Work Package can be completed within the constraints
How the community answered
(26 responses)- A4% (1)
- B15% (4)
- C73% (19)
- D8% (2)
Explanation
Explanation/Reference:
Topics
#Work Package#Accepting a Work Package#team manager#Managing Product Delivery