PRINCE2
PRINCE2-PRACTITIONER · Question #202
process of "Controlling a Stage" is the Risk Log updated? In which sub-
The correct answer is C. Examining Project Issues. Explanation/Reference:
Controlling a Stage
Question
process of "Controlling a Stage" is the Risk Log updated? In which sub-
Options
- ACapturing Project Issues
- BAssessing Progress
- CExamining Project Issues
- DReporting Highlights
How the community answered
(30 responses)- A17% (5)
- B3% (1)
- C70% (21)
- D10% (3)
Explanation
Explanation/Reference:
Topics
#Controlling a Stage#Risk Log#project issues#examining project issues
Community Discussion