Defining the stages of a project is fundamentally a process of balancing a number ofparameters. Which one of the following is NOT one of the parameters
The correct answer is A. The availability of the project board for progress meetings. Explanation/Reference:
Plans
Question
Defining the stages of a project is fundamentally a process of balancing a number ofparameters. Which one of the following is NOT one of the parameters
Options
- AThe availability of the project board for progress meetings
- BHow far ahead in the project it is sensible to plan
- CWhere the key decision points need to be on the project
- DToo many small stages versus too few big ones
How the community answered
(45 responses)- A84% (38)
- B9% (4)
- C2% (1)
- D4% (2)
Explanation
Explanation/Reference:
Topics
#management stages#stage planning#stage boundaries#decision points