PRINCE2-PRACTITIONER · Question #201

Defining the stages of a project is fundamentally a process of balancing a number ofparameters. Which one of the following is NOT one of the parameters

The correct answer is A. The availability of the project board for progress meetings. Explanation/Reference:

Plans

Question

Defining the stages of a project is fundamentally a process of balancing a number ofparameters. Which one of the following is NOT one of the parameters

Options

  • AThe availability of the project board for progress meetings
  • BHow far ahead in the project it is sensible to plan
  • CWhere the key decision points need to be on the project
  • DToo many small stages versus too few big ones

How the community answered

(45 responses)
  • A
    84% (38)
  • B
    9% (4)
  • C
    2% (1)
  • D
    4% (2)

Explanation

Explanation/Reference:

Topics

#management stages#stage planning#stage boundaries#decision points