PRINCE2-PRACTITIONER · Question #200

Which of these is NOT a specific objective of an end stage assessment?

The correct answer is B. Revise the Project Mandate. Explanation/Reference:

Managing Stage Boundaries

Question

Which of these is NOT a specific objective of an end stage assessment?

Options

  • APerform a risk analysis and management review of the project
  • BRevise the Project Mandate
  • CReview the tolerances set for the next Stage
  • DReview the next Stage Plan against the Project Plan

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    71% (15)
  • C
    10% (2)
  • D
    14% (3)

Explanation

Explanation/Reference:

Topics

#end stage assessment#stage boundaries#Project Mandate#project board