nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #169

Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

The correct answer is B. Review work package status. Explanation/Reference:

Controlling a Stage

Question

Which activity is responsible for updating the stage plan with actual during Controlling a Stage?

Options

  • AReview the stage status
  • BReview work package status
  • CReport Highlights
  • DTake corrective action

How the community answered

(38 responses)
  • A
    5% (2)
  • B
    82% (31)
  • C
    11% (4)
  • D
    3% (1)

Explanation

Explanation/Reference:

Topics

#Controlling a Stage#stage plan actuals#work package status#progress monitoring

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice