Which of the following is NOT a trigger for the project manager to authorize a work package?
The correct answer is D. Reporting highlights. Explanation/Reference:
Controlling a Stage
Question
Which of the following is NOT a trigger for the project manager to authorize a work package?
Options
- AStage Authorization
- BCorrective Action
- CException plan approved
- DReporting highlights
How the community answered
(24 responses)- A8% (2)
- B13% (3)
- C4% (1)
- D75% (18)
Explanation
Explanation/Reference:
Topics
#Controlling a Stage#Work Package authorization#process triggers#project management activities