nerdexam
PRINCE2

PRINCE2-PRACTITIONER · Question #168

Which of the following is NOT a trigger for the project manager to authorize a work package?

The correct answer is D. Reporting highlights. Explanation/Reference:

Controlling a Stage

Question

Which of the following is NOT a trigger for the project manager to authorize a work package?

Options

  • AStage Authorization
  • BCorrective Action
  • CException plan approved
  • DReporting highlights

How the community answered

(24 responses)
  • A
    8% (2)
  • B
    13% (3)
  • C
    4% (1)
  • D
    75% (18)

Explanation

Explanation/Reference:

Topics

#Controlling a Stage#Work Package authorization#process triggers#project management activities

Community Discussion

No community discussion yet for this question.

Full PRINCE2-PRACTITIONER Practice