PRINCE2-PRACTITIONER · Question #140

Which other management product is created when the Business case is updated during Initiating a Project?

The correct answer is C. Benefits Review plan. Explanation/Reference:

Business Case

Question

Which other management product is created when the Business case is updated during Initiating a Project?

Options

  • APost project review plan
  • BRisk Register
  • CBenefits Review plan
  • DIssue Register

How the community answered

(33 responses)
  • A
    3% (1)
  • B
    12% (4)
  • C
    79% (26)
  • D
    6% (2)

Explanation

Explanation/Reference:

Topics

#Business Case#Benefits Review Plan#Initiating a Project#management products

Community Discussion

No community discussion yet for this question.