Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by…

The correct answer is C. The total expected savings over 10 years, at current prices, is £20m. D. The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels. Explanation/Reference:

Business Case

Question

Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers' performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered:

  • Do nothing.
  • One service provider should be contracted to provide the services currently provided by the Information Technology Division and the Facilities Division.
  • A 10-year service contract should be agreed with the selected service provider.

The feasibility study developed high-level designs of the current organization, processes, systems and operating models, plus an outline Business Case for the required project. The external consultants also made the following recommendations for the management of the project:

Use PRINCE2. Set up the project with 4 management stages:

  • Stage 1. Standard PRINCE2 initiation activities.
  • Stage 2. Create detailed designs (future organization, processes, systems and operating models) and the service level agreement between MFH and the future

service provider.

  • Stage 3. Request and evaluate proposals, select service provider and agree contract.
  • Stage 4. Transfer equipment and staff, transfer responsibility for service provision and run trial period.

Initial estimates indicated that the project would cost £2.5m and take two years to complete. MFH senior management agreed that there was a case for outsourcing, and accepted the recommendations as a basis for the project. There is an expected saving of £20m over 10 years. The Outsourcing project has completed the Starting up a Project process and is now in the initiation stage. Because of the strategic importance of the project, the MFH Chief Executive Officer has taken the role of Executive. A PRINCE2-experienced Project Manager has been appointed from within MFH. Staff within the business functions being outsourced will work with the external consultants who conducted the feasibility study to define the detailed designs. Which 2 statements should be recorded under the Expected benefits heading?

Options

  • AThe 10-year outsourcing contract, at current prices, will be worth £80m.
  • BOutsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer.
  • CThe total expected savings over 10 years, at current prices, is £20m.
  • DThe 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels.
  • EThe confirmed cost of the Outsourcing project is £2.5m, but with considerable savings over 10 years.

How the community answered

(45 responses)
  • A
    7% (3)
  • B
    4% (2)
  • C
    76% (34)
  • E
    13% (6)

Explanation

Explanation/Reference:

Topics

#expected benefits#cost savings#Business Case#scenario analysis