PRINCE2-PRACTITIONER · Question #141
Who is responsible for the initial creation of the Configuration Item records?
The correct answer is D. Project Support. Explanation/Reference:
Change
Question
Who is responsible for the initial creation of the Configuration Item records?
Options
- AProject Manager
- BTeam Manager
- CProject Assurance
- DProject Support
How the community answered
(39 responses)- A3% (1)
- B13% (5)
- C5% (2)
- D79% (31)
Explanation
Explanation/Reference:
Topics
#Configuration Item Records#Project Support#configuration management#roles and responsibilities