PRINCE2-PRACTITIONER · Question #266
PRINCE2-PRACTITIONER Question #266: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-PRACTITIONER to reveal the answer and full explanation for question #266. The question stem and answer options stay visible for context.
Question
During stage 3, the project scope was extended to include a practice test for learners to take during the training course. The cost of this test will be included in the cost of the course. The change to project scope was approved and the cost of £2,500 was paid for from the change budget. The project manager documented an increase of £2,500 in the project budget in the business case. Is this an appropriate action, and why?
Options
- AYes, because the justification for the project should be recalculated based on the revised project budget.
- BYes, because the project manager determines which costs need to be updated at the end of each stage