PRINCE2-PRACTITIONER · Question #277
PRINCE2-PRACTITIONER Question #277: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-PRACTITIONER to reveal the answer and full explanation for question #277. The question stem and answer options stay visible for context.
Question
The project is now in stage 2. The 'training venue specifications' will not be delivered to schedule and the stage is forecast to exceed its time tolerance. As a result, the project manager has agreed with the team manager that the 'training venue specifications' will be delivered in stage 3 instead of stage 2. Is this an appropriate action, and why?
Options
- AYes, because the project manager should recommend corrective actions required.
- BYes, because moving the work enables stage 2 to be delivered within tolerance.
- CNo, because the team manager should inform the project manager by raising an issue.
- DNo, because the stage deviation should be referred to the project board for a decision.