- Question #202
In which sub-process of "Controlling a Stage" is the Risk Log updated?
- Question #203
which step is NOT part of "Accepting a Work Package"?
- Question #204
The configuration of the final deliverable of the project is -
- Question #205
Which of the following statements would NOT be included in the Project Product Description?
- Question #206
In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator
- Question #207
Which role is responsible for providing the customers quality expectations and acceptance criteria for the project?
- Question #208
Which management product defines the detailed nature purpose and function of a product?
- Question #209
Which of the following statements is False regarding the Risk Management Strategy'?
- Question #210
There are four steps in the Risk Management procedure, what are they?
- Question #211
Which of the following risk responses can be used for either an opportunity or a threat'?
- Question #212
Which of the following reports does not contain any information on risk?
- Question #213
Which of the following statements best describes what a risk owner is?
- Question #214
Who is responsible for reviewing the risk management practices to ensure they are in line with the project's risk management strategy?
- Question #215
Starting Up a project is triggered by which of the following?
- Question #216
Who is responsible for appointing the Project Manager?
- Question #217
During which of the following activities is the Project Product Description created?
- Question #218
Winch of the following is NOT an objective of Initiating a Project?
- Question #219
Which other management product is created when the Business case is updated during Initiating a Project'?
- Question #220
Who is responsible for the initial creation of the Configuration Item records?
- Question #221
In PRINCE2 what product is used to define the information that justifies the setting up, continuation or termination of the project?
- Question #222
Which product keeps track of Requests For Change?
- Question #223
In"Closing a Project"(CP)the project files are archiveD) What is the explanation given for this?
- Question #224
Which of the following statements is FALSE? Project Managers using PRINCE2TM are encouraged to...
- Question #225
Which of these is NOT a valid Risk Management action?
- Question #226
Which one of these is NOT a PRINCE2 Component?
- Question #227
Which document lists the major products of a plan with their key delivery dates?
- Question #228
The configuration of the final deliverable of the project is -
- Question #229
Which part of a product lifespan is not part of a project life cycle in the eyes of PRINCE2?
- Question #230
What is the first job carried out on receipt of a new Project Issue?
- Question #231
Which of these statements is FALSE?
- Question #232
Which of the following statements is FALSE?
- Question #233
Which one of these statements describes the true purpose of Acceptance Criteria?
- Question #234
How often does PRINCE2 recommend that open Project Issues should be reviewed?
- Question #235
What other product is reviewed at the end of each stage apart from the Business Case and Project Plan?
- Question #236
Why is a copy of the Project Issue always returned to the author?
- Question #237
Which of the options below reviews the benefits achieved by the project?
- Question #238
Which of these statements is FALSE?
- Question #239
The person best situated to keep an eye on a risk is called its...?
- Question #243
Identify the missing word in the following sentence... A PRINCE2 project focuses on the definition an d delivery of, in particular their quality requirements?
- Question #244
Which of the following is a TRUE principle of a PRINCE2 project?
- Question #245
Identify the missing words in the following sentence... A Project is a that is created for the purpose of delivering one or more business products according to an agreed Business C...
- Question #246
Which of the following statements is TRUE?
- Question #247
Which of the following statements is FALSE? PRINCE2 provides projects with . . .
- Question #248
Which of the following does PRINCE2 recognize as being project characteristics? 1. Projects are the means by which we introduce business change 2. Projects have a defined start and...
- Question #249
The PRINCE2 principle 'continued business justification' states that a requirement for a project is that... There is justifiable reason to start the project and justification shoul...
- Question #250
Which of the following PRINCE2 elements are described as being the aspects of project management that must be addressed continually and in parallel throughout the project?
- Question #251
Which of the following PRINCE2 elements are described as being the guiding obligations and good practices which determine whether the project is being managed using PRINCE2?
- Question #252
Which of the following are the integrated elements which make up the structure of PRINCE2?
- Question #253
Which of the following are benefits of using PRINCE2? 1. Provides a common vocabulary for all project participants, promoting effective communication 2. Promotes regular progress m...
- Question #254
The PRINCE2 principle 'focus on products' states that a successful project is which one of the following?