PRINCE2-FOUNDATION · Question #223

In"Closing a Project"(CP)the project files are archiveD) What is the explanation given for this?

The correct answer is D. To permit any future audit of the project' s actions. See the full explanation below for the reasoning.

Question

In“Closing a Project”(CP)the project files are archiveD) What is the explanation given for this?

Options

  • ATo provide useful lessons to future projects
  • BNever throw anything away.
  • CThis material may be needed by Programme Management
  • DTo permit any future audit of the project' s actions

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    9% (2)
  • D
    82% (18)