In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator
The correct answer is B. Project support. See the full explanation below for the reasoning.
Question
In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator
Options
- AProject manager
- BProject support
- CTeam Manager
- DProject Assurance
How the community answered
(20 responses)- A5% (1)
- B85% (17)
- C10% (2)