PRINCE2-FOUNDATION · Question #206

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator

The correct answer is B. Project support. See the full explanation below for the reasoning.

Question

In the PRINCE2 Quality review technique, who would most likely carry out the role of administrator

Options

  • AProject manager
  • BProject support
  • CTeam Manager
  • DProject Assurance

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    85% (17)
  • C
    10% (2)

Community Discussion

No community discussion yet for this question.