Which other management product is created when the Business case is updated during Initiating a Project'?
The correct answer is C. Benefits Review plan. See the full explanation below for the reasoning.
Question
Which other management product is created when the Business case is updated during Initiating a Project’?
Options
- APost project review plan
- BRisk Register
- CBenefits Review plan
- DIssue Register
How the community answered
(43 responses)- A14% (6)
- B5% (2)
- C74% (32)
- D7% (3)