Starting Up a project is triggered by which of the following?

The correct answer is D. Mandate. See the full explanation below for the reasoning.

Question

Starting Up a project is triggered by which of the following?

Options

  • ALegislation
  • BCorporate Strategy
  • CRisks
  • DMandate

How the community answered

(21 responses)
  • A
    14% (3)
  • B
    5% (1)
  • C
    5% (1)
  • D
    76% (16)