Who is responsible for appointing the Project Manager?

The correct answer is C. The Executive. See the full explanation below for the reasoning.

Question

Who is responsible for appointing the Project Manager?

Options

  • ACorporate or Programmer Management
  • BThe Project Board
  • CThe Executive
  • DProject Assurance

How the community answered

(61 responses)
  • A
    11% (7)
  • B
    5% (3)
  • C
    79% (48)