During which of the following activities is the Project Product Description created?

The correct answer is B. Prepare the outline business case. See the full explanation below for the reasoning.

Question

During which of the following activities is the Project Product Description created?

Options

  • ADesign and appoint the Project Management Team
  • BPrepare the outline business case
  • CSelect the project approach and assemble the project brief
  • DPlan the initiation stage

How the community answered

(59 responses)
  • A
    15% (9)
  • B
    71% (42)
  • C
    5% (3)
  • D
    8% (5)