PRINCE2-FOUNDATION · Question #221

In PRINCE2 what product is used to define the information that justifies the setting up, continuation or termination of the project?

The correct answer is B. Business Case. See the full explanation below for the reasoning.

Question

In PRINCE2 what product is used to define the information that justifies the setting up, continuation or termination of the project?

Options

  • AProject Initiation Document
  • BBusiness Case
  • CEnd Stage Approval
  • DProject Brief

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    83% (19)
  • D
    4% (1)

Community Discussion

No community discussion yet for this question.