What is the first job carried out on receipt of a new Project Issue?

The correct answer is B. Logging. See the full explanation below for the reasoning.

Question

What is the first job carried out on receipt of a new Project Issue?

Options

  • AAllocation of priority
  • BLogging
  • CDecision on what type of issue
  • DImpact Analysis

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    84% (26)
  • C
    10% (3)
  • D
    3% (1)