PRINCE2-FOUNDATION · Question #231

PRINCE2-FOUNDATION Question #231: Real Exam Question with Answer & Explanation

Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #231. The question stem and answer options stay visible for context.

Question

Which of these statements is FALSE?

Options

  • AThe Project Plan is an overview of the total project.
  • BFor each stage identified in the Project Plan, a Stage Plan is requireD)
  • CAn Exception Plan needs the approval of the next higher level of authority.
  • DA Team Plan needs approval by the Project BoarD)

Unlock PRINCE2-FOUNDATION to see the answer