PRINCE2-FOUNDATION · Question #232
PRINCE2-FOUNDATION Question #232: Real Exam Question with Answer & Explanation
Sign in or unlock PRINCE2-FOUNDATION to reveal the answer and full explanation for question #232. The question stem and answer options stay visible for context.
Question
Which of the following statements is FALSE?
Options
- ACustomer quality expectations should be discovered in the process "Starting Up a Project"
- BA company's QMS becomes part of PRINCE2
- CPRINCE2 may form part of a company's QMS
- DThe Stage Plan describes in detail how part of the Project Plan will be carried out
Unlock PRINCE2-FOUNDATION to see the answer
You've previewed enough free PRINCE2-FOUNDATION questions. Unlock PRINCE2-FOUNDATION for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.