Which of the following risk responses can be used for either an opportunity or a threat'?

The correct answer is B. Share. See the full explanation below for the reasoning.

Question

Which of the following risk responses can be used for either an opportunity or a threat’?

Options

  • AReduce
  • BShare
  • CReject
  • DEnhance

How the community answered

(25 responses)
  • A
    12% (3)
  • B
    76% (19)
  • C
    4% (1)
  • D
    8% (2)