PRINCE2-FOUNDATION · Question #202
In which sub-process of "Controlling a Stage" is the Risk Log updated?
The correct answer is C. Examining Project Issues. See the full explanation below for the reasoning.
Question
In which sub-process of “Controlling a Stage” is the Risk Log updated?
Options
- ACapturing Project Issues
- BAssessing Progress
- CExamining Project Issues
- DReporting Highlights
How the community answered
(45 responses)- A16% (7)
- B4% (2)
- C73% (33)
- D7% (3)