nerdexam
PeopleCert

PRINCE2-FOUNDATION · Question #202

In which sub-process of "Controlling a Stage" is the Risk Log updated?

The correct answer is C. Examining Project Issues. See the full explanation below for the reasoning.

Question

In which sub-process of “Controlling a Stage” is the Risk Log updated?

Options

  • ACapturing Project Issues
  • BAssessing Progress
  • CExamining Project Issues
  • DReporting Highlights

How the community answered

(45 responses)
  • A
    16% (7)
  • B
    4% (2)
  • C
    73% (33)
  • D
    7% (3)

Community Discussion

No community discussion yet for this question.

Full PRINCE2-FOUNDATION Practice