PeopleCert
PRINCE2-FOUNDATION · Question #201
Defining the stages of a project is fundamentally a process of balancing a number ofparameters. Which one of the following is NOT one of the parameters
The correct answer is A. The availability of the project board for progress meetings. See the full explanation below for the reasoning.
Question
Defining the stages of a project is fundamentally a process of balancing a number ofparameters. Which one of the following is NOT one of the parameters
Options
- AThe availability of the project board for progress meetings
- BHow far ahead in the project it is sensible to plan
- CWhere the key decision points need to be on the project
- DToo many small stages versus too few big ones
How the community answered
(29 responses)- A79% (23)
- B10% (3)
- C7% (2)
- D3% (1)
Community Discussion
No community discussion yet for this question.