Defining the stages of a project is fundamentally a process of balancing a number ofparameters. Which one of the following is NOT one of the parameters

The correct answer is A. The availability of the project board for progress meetings. See the full explanation below for the reasoning.

Question

Defining the stages of a project is fundamentally a process of balancing a number ofparameters. Which one of the following is NOT one of the parameters

Options

  • AThe availability of the project board for progress meetings
  • BHow far ahead in the project it is sensible to plan
  • CWhere the key decision points need to be on the project
  • DToo many small stages versus too few big ones

How the community answered

(29 responses)
  • A
    79% (23)
  • B
    10% (3)
  • C
    7% (2)
  • D
    3% (1)