PRINCE2-FOUNDATION · Question #200

Which of these is NOT a specific objective of an end stage assessment?

The correct answer is B. Revise the Project Mandate. See the full explanation below for the reasoning.

Question

Which of these is NOT a specific objective of an end stage assessment?

Options

  • APerform a risk analysis and management review of the project
  • BRevise the Project Mandate
  • CReview the tolerances set for the next Stage
  • DReview the next Stage Plan against the Project Plan

How the community answered

(61 responses)
  • A
    3% (2)
  • B
    80% (49)
  • C
    11% (7)
  • D
    5% (3)