PeopleCert
PRINCE2-FOUNDATION · Question #234
How often does PRINCE2 recommend that open Project Issues should be reviewed?
The correct answer is D. On a regular basis. See the full explanation below for the reasoning.
Question
How often does PRINCE2 recommend that open Project Issues should be reviewed?
Options
- AWeekly
- BAt Exception Assessments
- CAt Checkpoint Meetings
- DOn a regular basis
How the community answered
(31 responses)- A6% (2)
- B13% (4)
- C3% (1)
- D77% (24)
Community Discussion
No community discussion yet for this question.