PRINCE2-FOUNDATION · Question #228

The configuration of the final deliverable of the project is -

The correct answer is A. The sum total of its products. See the full explanation below for the reasoning.

Question

The configuration of the final deliverable of the project is -

Options

  • AThe sum total of its products
  • BThe interim products
  • CIts product description
  • DThe single end-product

How the community answered

(44 responses)
  • A
    70% (31)
  • B
    5% (2)
  • C
    16% (7)
  • D
    9% (4)