Which of the following statements is False regarding the Risk Management Strategy'?

The correct answer is A. It captures and maintains al relevant informant on identified threats and opportunists. See the full explanation below for the reasoning.

Question

Which of the following statements is False regarding the Risk Management Strategy’?

Options

  • AIt captures and maintains al relevant informant on identified threats and opportunists
  • BIt documents the r6k tolerances
  • CIt documents the approach to risk
  • DIt identifies responsible towards risk for the project

How the community answered

(26 responses)
  • A
    85% (22)
  • B
    4% (1)
  • C
    4% (1)
  • D
    8% (2)