- Question #103Elicitation and Collaboration
You have identified several problems that you need to track as the business analysis duties progress. You want to make certain that the identified activities are resolved. What doc...
problem trackingelicitation techniquesissue managementBA activities - Question #104Elicitation and Collaboration
You are the business analyst for your organization and are training Tracy on business analysis duties. You are explaining to Tracy how it's important for a business analyst to gene...
creative thinkinganalytical thinkingidea generationlateral thinking - Question #105Elicitation and Collaboration
What requirements elicitation technique examines the available information, documentation, records, and history of a solution, organization, or cause to identify relevant informati...
document analysiselicitation techniquesinformation gatheringrequirements documentation - Question #106Elicitation and Collaboration
What type of requirements elicitation technique is the Delphi Technique?
Delphi techniquesurveyelicitation techniquesconsensus building - Question #107Requirements Analysis and Design Definition
Yolanda is the web designer for your company and you are the business analyst. You are working with Yolanda on a new website that your company will host. You'd like for her to crea...
horizontal prototypeprototypingUI mockuprequirements visualization - Question #108Elicitation and Collaboration
You are the business analyst for your organization and need a method to requirements elicitation from nearly 12,000 stakeholders. You want a method to quickly capture this group's...
surveyslarge-scale elicitationstakeholder engagementquantitative elicitation - Question #109Requirements Analysis and Design Definition
You are creating a model that shows how data moves through a system. Each function that modifies the data in any manner is identified, decomposed to smaller levels, and the system...
data flow diagramsmodeling techniquessystem analysisfunctional decomposition - Question #110Requirements Analysis and Design Definition
Wanda is the business analyst for her organization and she is currently working on the specify and model requirements process. One of the elements of this process is the documentat...
textual requirementsrequirements specificationconstraintscapabilities - Question #111Elicitation and Collaboration
You are the business analyst for your organization and are preparing for the conduct elicitation activities. You'll have six inputs as you prepare for this activity. Which one of t...
elicitation inputsrequirements management plansolution scopeprocess inputs - Question #112Elicitation and Collaboration
You are the business analyst for your organization. You want to use a requirements elicitation technique to produce a broad set of options for an identified problem. You want the s...
brainstormingelicitation techniquesoption generationstakeholder collaboration - Question #113Business Analysis Planning and Monitoring
You are currently working on creating the activity list for an initiative in your organization. What characteristic must be assigned to each task in your task list?
activity listtask planningwork managementunique identifiers - Question #114Elicitation and Collaboration
You have identified several stakeholders that you believe are kinesthetic learners. Which statement best describes the kinesthetic learning approach?
kinesthetic learninglearning stylesstakeholder communicationexperiential learning - Question #115Strategy Analysis
Holly is the business analyst for her organization. Management has asked Holly to create a document that will define solution alternatives and how each identified solution may prov...
feasibility studysolution alternativesbusiness casecost-benefit analysis - Question #116Requirements Life Cycle Management
All of the following stakeholders participate in the prioritization of requirements except for which one?
requirements prioritizationstakeholder rolesrequirements managementproject team - Question #117Elicitation and Collaboration
You are completing the prepare for elicitation process for an identified problem in your organization. The prepare for elicitation process requires three inputs for this process. W...
elicitation preparationelicitation inputsstakeholder listsolution scope - Question #118Business Analysis Planning and Monitoring
Which of the following tasks does not rely on other activities, and no other activities rely on this task completing?
task dependenciesindependent tasksactivity sequencingscheduling - Question #119Strategy Analysis
Which of the following processes can start with the source of problems or with the problem itself?
risk identificationrisk managementproblem sourcesrisk analysis - Question #120Strategy Analysis
In risk analysis, which of the following can be identified as a consequence of a disaster?
risk analysisdisaster consequencesoperational lossbusiness impact - Question #121Solution Evaluation
____ is a process to determine the completeness of the project work and to gain the customer's acceptance to move the project forward.
scope verificationcustomer acceptancephase gatedeliverable completion - Question #122Strategy Analysis
Which of the following phases is the first step towards creating a business continuity plan?
business continuity planningBCP phasesscope initiationdisaster recovery - Question #123Solution Evaluation
Which of the following charts is a quality control tool to show categories of defects?
Pareto chartquality controldefect categorizationquality tools - Question #124Business Analysis Planning and Monitoring
Which one of the following diagrams when properly laid out is always laid in a left to right display to properly reflect the chronology of all project work?
schedule network diagramproject schedulingchronologyproject planning - Question #125Business Analysis Planning and Monitoring
Which of the following is a visual decomposition of the program scope and the resources needed in order to create the things defined within the program scope?
resource breakdown structureprogram scopedecompositionresource planning - Question #126Business Analysis Planning and Monitoring
When does the lessons learned document is updated?
lessons learnedproject lifecycleknowledge managementcontinuous improvement - Question #127Strategy Analysis
Which of the following stages of a project defines the number of risks and opportunities, including intense planning and anticipation of risk events?
risk identificationinitiation phaseproject phasesrisk opportunities - Question #128Elicitation and Collaboration
Which of the following roles works with the project team to understand the deliverables and then teaches the users of the deliverables how to utilize the project's product?
trainer rolestakeholder rolesuser trainingproject roles - Question #129Strategy Analysis
Which of the following qualitative techniques involves a disciplined analysis of the event sequences that could transform a potential hazard into an accident?
Preliminary Risk Analysisqualitative risk techniquehazard analysisrisk methods - Question #130Strategy Analysis
Which of the following establishes organizational checks and balances with a proper segregation of front, back, and middle office functions for effective risk management?
risk governancesegregation of dutiesorganizational controlschecks and balances - Question #131Business Analysis Planning and Monitoring
As a program manager, you decided to overlap two phases of your program. Which of the following terms best describe your act?
fast trackingschedule compressionphase overlapprogram management - Question #132Business Analysis Planning and Monitoring
Which of the following software development life cycles is a methodology that divides the project into phases, and the project manager focuses on control of time, cost, and scope?
waterfall methodologySDLCproject phasestraditional methodology - Question #133Business Analysis Planning and Monitoring
Which of the following graphical presentations of a project plan is most appropriate for presenting to upper management?
Critical Path Methodmanagement reportingproject schedulingexecutive communication - Question #134Strategy Analysis
Which of the following diagrams is used to display sensitivity analysis data?
tornado diagramsensitivity analysisrisk visualizationdata presentation - Question #135Business Analysis Planning and Monitoring
Which of the following is a visual decomposition of the project scope?
Work Breakdown Structurescope decompositionproject scopeproject planning - Question #136Business Analysis Planning and Monitoring
________ are timeless events that show progress in the project. These are typically achieved at the end of phase in the project lifecycle.
milestonesproject progressphase completionproject lifecycle - Question #137Strategy Analysis
Which of the following authorizes the project to exist within the organization?
project charterproject authorizationproject initiationgovernance - Question #138Business Analysis Planning and Monitoring
Which of the following tasks cannot start until other tasks are completed?
task dependenciesdependent tasksschedule logicpredecessor relationships - Question #139Requirements Life Cycle Management
Which of the following roles approves the project scope statement, phase gate reviews, solution validations, scope changes, and project success criteria?
solution ownerscope approvalstakeholder rolesgovernance - Question #140Strategy Analysis
Which of the following processes includes tasks and roles, risk categories, schedules for risk management activities, definitions of probability and impact, and the stakeholders' t...
risk management planrisk categoriesprobability and impactrisk planning - Question #141Strategy Analysis
Which of the following is the process of identifying and assessing factors that may jeopardize the success of a project or the achievement of a goal?
risk analysisrisk identificationrisk assessmentproject risks - Question #142Business Analysis Planning and Monitoring
As a milestone is reached, the project is funded for enough capital to reach the next milestone. This approach is called _________.
step fundingmilestone-based financingproject funding approachcapital allocation - Question #143Business Analysis Planning and Monitoring
Which of the following roles helps assess the data requirements of a project, identifies data assets, and helps the project team complete data modeling requirements?
information architectstakeholder rolesdata modelingdata assets - Question #144Strategy Analysis
Which of the following processes is used by organizations to set the risk tolerance, identify the potential risks, and prioritize the tolerance for risk?
risk managementrisk tolerancerisk identificationorganizational risk - Question #145Business Analysis Planning and Monitoring
Which of the following terms is used to describe a major deliverable or key even in the project used to measure project progress?
milestoneproject life cycleproject progresskey deliverable - Question #146Strategy Analysis
Which of the following is the process of analyzing the areas of a project that are most affected by risk?
risk categorizationrisk analysisrisk areasproject risk - Question #147Business Analysis Planning and Monitoring
Which of the following chart is important to ensure
RACI chartresponsibility assignmentstakeholder rolesaccountability - Question #148Strategy Analysis
Which of the following quantitative risk analysis techniques relies on experience and past data to compute the probability and impact of risks on project objectives?
quantitative risk analysisinterviewing techniqueprobabilityrisk impact - Question #149Business Analysis Planning and Monitoring
Which of the following types of charts shows which resources are needed in the project and allows you to group the resources by project phase or other attributes?
Resource Breakdown Structureresource managementproject phasesresource planning - Question #150Elicitation and Collaboration
Which of the following types of elicitation allows each stakeholder to freely discuss their role in a particular process?
unstructured interviewelicitation techniquesstakeholder discussionrequirements gathering - Question #151Business Analysis Planning and Monitoring
Which of the following chart shows the correlation between project team members and the work they've been assigned to complete?
RAM chartresponsibility assignmentteam memberswork assignment - Question #152Elicitation and Collaboration
Which of the following participants have to keep the minutes and details of the conversation during Interviews?
interview rolesscribeelicitation techniquesmeeting documentation