nerdexam
IIBA

CBAP · Question #137

Which of the following authorizes the project to exist within the organization?

The correct answer is A. Project charter. The project charter is the formal document that officially authorizes a project to exist and grants the project manager authority to use organizational resources.

Strategy Analysis

Question

Which of the following authorizes the project to exist within the organization?

Options

  • AProject charter
  • BProject network diagram
  • CProject integration management
  • DProject boundaries

How the community answered

(56 responses)
  • A
    82% (46)
  • B
    2% (1)
  • C
    11% (6)
  • D
    5% (3)

Why each option

The project charter is the formal document that officially authorizes a project to exist and grants the project manager authority to use organizational resources.

AProject charterCorrect

The project charter formally authorizes the project to exist within the organization and is signed by a sponsor or senior management. It grants the project manager the authority to apply organizational resources to project activities. Without the charter, the project has no formal standing within the organization.

BProject network diagram

A project network diagram is a scheduling tool that visually represents task sequencing and dependencies, not a document that grants project authorization.

CProject integration management

Project integration management is a PMBOK knowledge area focused on coordinating all project processes and work, not a document that authorizes the project.

DProject boundaries

Project boundaries define what is included in and excluded from the project scope, but do not serve as the formal authorization mechanism for the project.

Concept tested: Project charter as formal project authorization document

Topics

#project charter#project authorization#project initiation#governance