CBAP · Question #137
Which of the following authorizes the project to exist within the organization?
The correct answer is A. Project charter. The project charter is the formal document that officially authorizes a project to exist and grants the project manager authority to use organizational resources.
Question
Which of the following authorizes the project to exist within the organization?
Options
- AProject charter
- BProject network diagram
- CProject integration management
- DProject boundaries
How the community answered
(56 responses)- A82% (46)
- B2% (1)
- C11% (6)
- D5% (3)
Why each option
The project charter is the formal document that officially authorizes a project to exist and grants the project manager authority to use organizational resources.
The project charter formally authorizes the project to exist within the organization and is signed by a sponsor or senior management. It grants the project manager the authority to apply organizational resources to project activities. Without the charter, the project has no formal standing within the organization.
A project network diagram is a scheduling tool that visually represents task sequencing and dependencies, not a document that grants project authorization.
Project integration management is a PMBOK knowledge area focused on coordinating all project processes and work, not a document that authorizes the project.
Project boundaries define what is included in and excluded from the project scope, but do not serve as the formal authorization mechanism for the project.
Concept tested: Project charter as formal project authorization document