CBAP · Question #145

Which of the following terms is used to describe a major deliverable or key even in the project used to measure project progress?

The correct answer is D. Milestone. A milestone is the standard project management term for a major deliverable or key event used to measure project progress.

Business Analysis Planning and Monitoring

Question

Which of the following terms is used to describe a major deliverable or key even in the project used to measure project progress?

Options

  • AProject life cycle
  • BPhase
  • CAchievement
  • DMilestone

How the community answered

(19 responses)
  • A
    5% (1)
  • C
    11% (2)
  • D
    84% (16)

Why each option

A milestone is the standard project management term for a major deliverable or key event used to measure project progress.

AProject life cycle

Project life cycle describes the entire sequence of phases a project passes through from initiation to closure, not a single measurable event.

BPhase

A phase is a defined collection of related project activities that culminates in a deliverable, representing a time period rather than a specific measurable point.

CAchievement

Achievement is not a recognized project management term in standard frameworks like PMBOK or CompTIA Project+.

DMilestoneCorrect

A milestone marks a significant point in a project schedule, such as the completion of a major deliverable or phase gate, and is used specifically to track and communicate project progress. Unlike tasks, milestones have no duration - they represent a moment in time that signals something important has been achieved. This term is standardized in both PMI's PMBOK Guide and CompTIA Project+ curricula.

Concept tested: Project milestone definition and purpose

Source: https://www.pmi.org/learning/library/milestones-project-management-7670