CBAP · Question #145
Which of the following terms is used to describe a major deliverable or key even in the project used to measure project progress?
The correct answer is D. Milestone. A milestone is the standard project management term for a major deliverable or key event used to measure project progress.
Question
Which of the following terms is used to describe a major deliverable or key even in the project used to measure project progress?
Options
- AProject life cycle
- BPhase
- CAchievement
- DMilestone
How the community answered
(19 responses)- A5% (1)
- C11% (2)
- D84% (16)
Why each option
A milestone is the standard project management term for a major deliverable or key event used to measure project progress.
Project life cycle describes the entire sequence of phases a project passes through from initiation to closure, not a single measurable event.
A phase is a defined collection of related project activities that culminates in a deliverable, representing a time period rather than a specific measurable point.
Achievement is not a recognized project management term in standard frameworks like PMBOK or CompTIA Project+.
A milestone marks a significant point in a project schedule, such as the completion of a major deliverable or phase gate, and is used specifically to track and communicate project progress. Unlike tasks, milestones have no duration - they represent a moment in time that signals something important has been achieved. This term is standardized in both PMI's PMBOK Guide and CompTIA Project+ curricula.
Concept tested: Project milestone definition and purpose