CBAP · Question #116
All of the following stakeholders participate in the prioritization of requirements except for which one?
The correct answer is D. Project team. The general project team does not participate in requirements prioritization; only stakeholders with specific decision-making authority or subject matter expertise perform that activity.
Question
All of the following stakeholders participate in the prioritization of requirements except for which one?
Options
- AProject manager
- BImplementation subject matter expert
- CDomain subject matter expert
- DProject team
How the community answered
(33 responses)- A9% (3)
- B3% (1)
- C6% (2)
- D82% (27)
Why each option
The general project team does not participate in requirements prioritization; only stakeholders with specific decision-making authority or subject matter expertise perform that activity.
The project manager participates in prioritization to balance requirements against project constraints such as schedule, budget, and scope.
Implementation SMEs contribute by evaluating technical complexity and implementation effort, which directly informs how requirements should be ranked.
Domain SMEs provide business context and relative business value assessments that are essential to evaluating and ranking requirements accurately.
Requirements prioritization requires input from stakeholders who can assess business value, technical feasibility, and project constraints - roles specifically filled by the project manager, domain SMEs, and implementation SMEs. The project team as a collective executes work based on already-prioritized requirements but does not hold the authority or specialized perspective needed to make prioritization decisions. Prioritization responsibility rests with those accountable for project outcomes and those with domain or technical expertise.
Concept tested: Stakeholder participation in requirements prioritization
Source: https://www.iiba.org/babok-guide/
Topics
Community Discussion
No community discussion yet for this question.