During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the Business analyst (BA). The BA became aware of the new…

The correct answer is C. change control process. A change control process is the formal mechanism that ensures all requirement or design changes are reviewed, approved, and communicated to the BA and relevant stakeholders before implementation.

Requirements Life Cycle Management

Question

During the testing phase, a new requirement surfaced and the stakeholder asked the developer to modify the code without informing the Business analyst (BA). The BA became aware of the new functionality after a defect was raised against another component of the design. The BA can keep this situation from occurring in the future by creating a:

Options

  • Arisk strategy.
  • Bprioritization approach.
  • Cchange control process.
  • Dstakeholder engagement plan.

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    3% (1)
  • C
    76% (29)
  • D
    13% (5)

Why each option

A change control process is the formal mechanism that ensures all requirement or design changes are reviewed, approved, and communicated to the BA and relevant stakeholders before implementation.

Arisk strategy.

A risk strategy addresses potential threats to the project but does not govern how changes to requirements or design are submitted, approved, and communicated.

Bprioritization approach.

A prioritization approach ranks requirements by business value or urgency but provides no mechanism to control or track how changes enter the project.

Cchange control process.Correct

A change control process establishes defined procedures for submitting, reviewing, approving, and communicating changes to requirements or solution design, ensuring the BA is always informed before modifications are made. Without it, developers can implement undocumented changes that create defects and break traceability between requirements and the solution. Formalizing this process prevents ad hoc modifications and keeps all parties aligned on the current baseline.

Dstakeholder engagement plan.

A stakeholder engagement plan defines communication approaches and responsibilities but does not enforce a formal change submission and approval workflow.

Concept tested: Change control process for managing requirement changes

Topics

#change control process#unauthorized changes#requirements management#scope management