CBAP · Question #126
When does the lessons learned document is updated?
The correct answer is D. Throughout the project lifecycle.. Lessons learned are captured and updated continuously throughout all project phases to ensure timely documentation of insights from every stage.
Question
When does the lessons learned document is updated?
Options
- AAt planning phase.
- BAt execution phase.
- CAt closing phase.
- DThroughout the project lifecycle.
How the community answered
(44 responses)- A2% (1)
- B7% (3)
- C16% (7)
- D75% (33)
Why each option
Lessons learned are captured and updated continuously throughout all project phases to ensure timely documentation of insights from every stage.
Updating lessons learned only during planning ignores valuable insights gained during execution, monitoring and controlling, and closing.
Limiting updates to the execution phase misses critical reflections from planning decisions and final outcome evaluations in the closing phase.
While the closing phase includes a formal lessons learned review, waiting until closing means real-time insights from earlier phases are likely lost or forgotten by the time they are documented.
According to PMI's PMBOK Guide, lessons learned are identified, documented, and updated throughout all phases of the project lifecycle - from initiation through closing. Capturing them continuously ensures insights from early phases can inform later phases, preventing knowledge loss. Restricting documentation to a single phase results in incomplete records and forgotten details.
Concept tested: Lessons learned documentation timing across project lifecycle
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok