nerdexam
IIBA

CBAP · Question #133

CBAP Question #133: Real Exam Question with Answer & Explanation

The correct answer is C. Critical Path Method. The Critical Path Method (CPM) is the standard graphical project plan tool used to communicate schedule, task dependencies, and project timeline - making it the most appropriate choice for presenting a project plan to upper management.

Question

Which of the following graphical presentations of a project plan is most appropriate for presenting to upper management?

Options

  • APie chart
  • BPareto Chat
  • CCritical Path Method
  • DScatter chart

Explanation

The Critical Path Method (CPM) is the standard graphical project plan tool used to communicate schedule, task dependencies, and project timeline - making it the most appropriate choice for presenting a project plan to upper management.

Common mistakes.

  • A. A pie chart shows proportional data distributions and is not a tool for representing a project plan or schedule.
  • B. A Pareto chart is a quality management tool used to identify the most significant causes of defects or problems, not to present a project plan.
  • D. A scatter chart displays correlations between two variables and is not suited for representing a project schedule or plan.

Concept tested. Critical Path Method as project plan visualization

Reference. https://www.pmi.org/learning/library/critical-path-method-scheduling-6994

Community Discussion

No community discussion yet for this question.

Full CBAP Practice
Which of the following graphical presentations of a project plan... | CBAP Q#133 Answer | NerdExam