CBAP · Question #121

____ is a process to determine the completeness of the project work and to gain the customer's acceptance to move the project forward.

The correct answer is C. Verify scope. Verify Scope (also called Validate Scope in PMBOK 6) is the formal process of reviewing deliverables with the customer to confirm completeness and obtain acceptance before moving forward.

Solution Evaluation

Question

____ is a process to determine the completeness of the project work and to gain the customer's acceptance to move the project forward.

Options

  • APhase gate review
  • BInspection of key results
  • CVerify scope
  • DQuality control

How the community answered

(51 responses)
  • A
    6% (3)
  • B
    4% (2)
  • C
    80% (41)
  • D
    10% (5)

Why each option

Verify Scope (also called Validate Scope in PMBOK 6) is the formal process of reviewing deliverables with the customer to confirm completeness and obtain acceptance before moving forward.

APhase gate review

A phase gate review is a decision checkpoint at the end of a project phase to evaluate whether to continue, not a formal process for obtaining customer acceptance of deliverables.

BInspection of key results

Inspection of key results is a technique used within quality or scope processes, not a named process that encompasses the full cycle of completeness verification and customer sign-off.

CVerify scopeCorrect

Verify Scope is the specific project management process in which completed deliverables are reviewed with the customer or sponsor to ensure they meet acceptance criteria. It formalizes acceptance and provides sign-off, allowing the project to proceed to the next phase or close out the current one. This process directly addresses both completeness of work and customer acceptance.

DQuality control

Quality control focuses on monitoring and recording results of quality activities to assess performance, not on formally obtaining customer acceptance of deliverables.

Concept tested: Validate/Verify Scope process in project management

Source: https://www.pmi.org/learning/library/validate-scope-process-6085

Topics

#scope verification#customer acceptance#phase gate#deliverable completion