C_TPLM22_67 Exam Questions
198 real C_TPLM22_67 exam questions with expert-verified answers and explanations. Page 1 of 4.
- Question #1
Which indicator of the event scenario specifies whether the time interval can be changed manually in the application or not? Please choose the correct answer. Response:
- Question #2
Which version serves as a proof of the project status in the past and also serves as a comparison with the operative project? Please choose the correct answer. Response:
- Question #3
Which of the following related to an activity stipulates the activity type and determines how an activity is handled during calculation, scheduling and capacity planning? Please ch...
- Question #4
How can the capacity requirements of an activity be reduced? There are 3 correct answers to this question. Response:
- Question #5
How do you evaluate and display details of orders and networks that create capacityrequirements at the work centers? Please choose the correct answer. Response:
- Question #6
In which of the following levels can you execute BOM transfer in the order browser? There are 3 correct answers to this question. Response:
- Question #7
What is the starting point for milestone billing? Please choose the correct answer. Response:
- Question #8
Which type of billing is generally used in plant engineering and construction projects? Please choose the correct answer. Response:
- Question #9
You are using the billing and down payment processing in Sales and Distribution and updating the actual data to billing elements in the project system. Which of the following busin...
- Question #10
In bottom-up time scheduling scenario the differences between the earliest and latest dates of an activity are referred to as? Please choose the correct answer. Response:
- Question #11
In which transactions can you specify whether networks are scheduled together with maintenance orders that have been assigned as sub networks? There are 2 correct answers to this q...
- Question #12
Which of the following type determines which type of orders a system can create during assembly processing? Please choose the correct answer. Response:
- Question #13
Which of the following are used when you use the SAP Document Management System in Project System to assign document info records? There are 2 correct answers to this question. Res...
- Question #14
Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships? Please choose...
- Question #15
Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items? Please choose the correct answer. Response:
- Question #16
Your projects consist of WBS elements, several networks, and subnetworks.What are the advantages of new overall network scheduling (CN24N) instead of the old overall network schedu...
- Question #17
What do you choose when creating a new network by copying an operative network? There are 3 correct answers to this question. Response:
- Question #18
Which of the following combination of assignment to an externally-processed activity allows you to carry out capacity planning for your vendors? Please choose the correct answer. R...
- Question #19
What are the various elements that are included in checking rules? There are 3 correct answers to this question. Response:
- Question #20
Which of the following documents the processing status of activities and activity elements in a network and enables you to make forecasts as to how the project will progress? Pleas...
- Question #21
Which of the following do you have to create for services to be performed by external resources instead of using externally processed activities? There are 2 correct answers to thi...
- Question #22
In resource-related billing if you do not want to bill a customer for a dynamic item, where do you enter this information? Please choose the correct answer. Response:
- Question #23
In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged a...
- Question #24
What are the different views available for capacity planning and work center planning? There are 2 correct answers to this question. Response:
- Question #25
Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks. How do you ensure th...
- Question #26
Which of the following prerequisites need to be met in order to analyze the capacity requirements of an activity? There are 3 correct answers to this question. Response:
- Question #27
How can you distinguish between service activities and external activities while accessing the detailed information for service activities on the external tab page? There are 2 cor...
- Question #28
In which of the following transactions the profile for WBS scheduling is used for scheduling in the project planning board? There are 2 correct answers to this question. Response:
- Question #29
Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response? Please choose the correct answer. Response:
- Question #30
You have implemented Activity-Based Costing to allocate business process overhead costs to your projects. Which data in the project is used to find the appropriate business process...
- Question #31
Project System has its own Organizational structure, which can be a matrix structure. Please choose the correct answer. Response:
- Question #32
How do you create a detailed payment schedule if the expense for an external activity or purchased component is not paid with a single invoice? Please choose the correct answer. Re...
- Question #33
Which method of revenue planning allows you to follow the same procedure as in hierarchical cost planning or can be entered by revenue element? Please choose the correct answer. Re...
- Question #34
Which of the following ensures that a claim arising from variances is prepared and lodged against the contractual partners at the right time or deflected if it is in the other dire...
- Question #35
What is the transaction code for editing the planning profile? Please choose the correct answer. Response:
- Question #36
In which type of billing do you assign the posting to the down payment request when you post the incoming payment for a down payment? Please choose the correct answer. Response:
- Question #37
How can you determine the degree of control yourself if you are managing material in plant stock or according to individual WBS element where you have no control over procurement o...
- Question #38
How are cost-relevant items determined for stock materials while using planned costs in networks? Please choose the correct answer. Response:
- Question #39
Which type of network does not allow you to assign materials directly, but only indirectly using a bill of materials? Please choose the correct answer. Response:
- Question #40
When using budgeting and active availability control, which business transactions affect the current budget? There are 3 correct answers to this question. Response:
- Question #41
If a component and the upper-level activity have different delivery information. Which of the following has priority for the component? Please choose the correct answer. Response:
- Question #42
In which type of settlement the costs of all the periods up to the one you specify in settlement are settled? Please choose the correct answer. Response:
- Question #43
What are the two basic elements that SAP Project system provides for mapping the structures of projects? There are 2 correct answers to this question. Response:
- Question #44
Which of the available capacity leveling methods for networks/activities allows you to select a particular work center and display a capacity load curve that shows both the capacit...
- Question #45
Which type of order is created at BOM level to cover requirements when a material shortage occurs in material planning? Please choose the correct answer. Response:
- Question #46
Which of the views available in structure oriented planning displays the planned costs of appended orders or network activities assigned to the WBS element? Please choose the corre...
- Question #47
Which of the following decides whether networks can be header assigned or activity-assigned? There are 2 correct answers to this question. Response:
- Question #48
What do you call a closed sequence of relationships and activities where you start from an activity and end up back at the same activity, by way of relationships? Please choose the...
- Question #49
Which account category is used for account assignment of orders, which includes network headers, network activities, maintenance orders, internal orders and manufacturing orders? P...
- Question #50
What is the procurement element for requirements planning? Please choose the correct answer. Response: