C_TPLM22_67 · Question #46

Which of the views available in structure oriented planning displays the planned costs of appended orders or network activities assigned to the WBS element? Please choose the correct answer. Response:

The correct answer is A. Order/Network view. See the full explanation below for the reasoning.

Question

Which of the views available in structure oriented planning displays the planned costs of appended orders or network activities assigned to the WBS element? Please choose the correct answer. Response:

Options

  • AOrder/Network view
  • BCumulative view
  • CDistributed view
  • DPlanned total

How the community answered

(33 responses)
  • A
    79% (26)
  • B
    6% (2)
  • C
    12% (4)
  • D
    3% (1)