SAP
C_TPLM22_67 · Question #47
Which of the following decides whether networks can be header assigned or activity-assigned? There are 2 correct answers to this question. Response:
The correct answer is A. Order type C. Plant. See the full explanation below for the reasoning.
Question
Which of the following decides whether networks can be header assigned or activity-assigned? There are 2 correct answers to this question. Response:
Options
- AOrder type
- BBilling type
- CPlant
- DNetwork structure
How the community answered
(47 responses)- A72% (34)
- B19% (9)
- D9% (4)
Community Discussion
No community discussion yet for this question.