C_TPLM22_67 · Question #23
In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account…
The correct answer is A. It can be copied to a new project B. Cost planning can be moved automatically along with the activities D. This assignment can then be used to display the planned costs of the orders of the project. See the full explanation below for the reasoning.
Question
In addition to manual planning in the WBS, you sometimes assign different types of orders (internal orders or maintenance orders, for example) to the WBS element that are flagged as account assignment elements. What is the use of this assignment? There are 3 correct answers to this question. Response:
Options
- AIt can be copied to a new project
- BCost planning can be moved automatically along with the activities
- CThis assignment can then be used to display the unit costs of the orders of the project
- DThis assignment can then be used to display the planned costs of the orders of the project
How the community answered
(64 responses)- A84% (54)
- C16% (10)