Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items? Please choose the correct answer. Response:
The correct answer is B. Preliminary purchase requisition. See the full explanation below for the reasoning.
Question
Which indicator is set for assemblies that need to be ordered well in advance of consumption and are allocated as stock items? Please choose the correct answer. Response:
Options
- APlanned independent requirement
- BPreliminary purchase requisition
- CThird party purchase requisition
- DPlanned purchase requisition
How the community answered
(50 responses)- A10% (5)
- B84% (42)
- C4% (2)