Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships? Please choose the correct…

The correct answer is D. Mass change function. See the full explanation below for the reasoning.

Question

Which function allows you to make cross-project changes to fields pertaining to project definitions, WBS elements, networks, activities, milestones and relationships? Please choose the correct answer. Response:

Options

  • AMass document function
  • BWork function
  • CAuthorization function
  • DMass change function

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    5% (2)
  • C
    3% (1)
  • D
    84% (32)