C_TPLM22_67 · Question #28
In which of the following transactions the profile for WBS scheduling is used for scheduling in the project planning board? There are 2 correct answers to this question. Response:
The correct answer is A. CJ29 B. CJ2B. See the full explanation below for the reasoning.
Question
In which of the following transactions the profile for WBS scheduling is used for scheduling in the project planning board? There are 2 correct answers to this question. Response:
Options
- ACJ29
- BCJ2B
- CCJ30
- DCJ2A
How the community answered
(39 responses)- A85% (33)
- C5% (2)
- D10% (4)
Community Discussion
No community discussion yet for this question.