In which of the following transactions the profile for WBS scheduling is used for scheduling in the project planning board? There are 2 correct answers to this question. Response:

The correct answer is A. CJ29 B. CJ2B. See the full explanation below for the reasoning.

Question

In which of the following transactions the profile for WBS scheduling is used for scheduling in the project planning board? There are 2 correct answers to this question. Response:

Options

  • ACJ29
  • BCJ2B
  • CCJ30
  • DCJ2A

How the community answered

(39 responses)
  • A
    85% (33)
  • C
    5% (2)
  • D
    10% (4)