C_TPLM22_67 · Question #29

Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response? Please choose the correct answer. Response:

The correct answer is B. Availability control. See the full explanation below for the reasoning.

Question

Which of the following can promptly identify commitments for a project that are too high and trigger various actions in response? Please choose the correct answer. Response:

Options

  • ATolerance limit
  • BAvailability control
  • CTime horizon
  • DBudget plan

How the community answered

(37 responses)
  • A
    5% (2)
  • B
    73% (27)
  • C
    16% (6)
  • D
    5% (2)